ABC Research Finds Multiskilling Can Reduce Construction Schedules by Up to 38%
Key Highlights
- ABC research analyzed nearly 90,000 labor hours across 18 construction projects and found that multiskilled crews completed work in 22% to 38% fewer workdays than a modeled single-trade strategy
- Researchers documented 80 unique trade and skill combinations, with multiskilled workers performing an average of 3.2 different trades or skills during their projects
- The three-part research series found that multiskilling increased production rates by 37% to 50%, reduced waiting and idle time by 68% and improved workforce flexibility
WASHINGTON, DC — Multiskilled construction crews can complete projects in approximately 22% to 38% fewer workdays than a modeled single-trade labor strategy, according to new research released by Associated Builders and Contractors (ABC). The findings suggest that expanding workers' skills can help contractors improve workforce utilization, manage labor constraints and meet construction demand without relying solely on additional workers.
Conducted by the Simplar Foundation, the research is the final report in a three-part series examining the effects of multiskilling on construction workforce performance. Together, the studies document improvements in productivity, workforce utilization and project schedules when qualified craft professionals can apply multiple skills across project tasks.
“America faces a fundamental challenge: We have more to build than our workforce can currently support," said Michael Bellaman, ABC president and CEO. “This research demonstrates that a solution is already within reach. By investing in our craft professionals, expanding their skills and removing unnecessary barriers to using those skills, we can create more opportunity for workers and greater capacity for contractors to build America.
“As a new Congress prepares to take office, lawmakers now have powerful evidence to guide policies that strengthen our workforce, promote fair and open competition and deliver better outcomes for owners and taxpayers. This is an opportunity for the entire construction industry to win.”
Multiskilled Crews Reduce Project Workdays
The report, Schedule Duration and Labor-Curve Outcomes Associated with a Multiskilled Labor Strategy, analyzed nearly 90,000 labor hours across 18 construction projects involving 11 contractors. Researchers examined actual project labor records to evaluate how multiskilled workers helped contractors match available skills to changing project needs, maintain workflow continuity and manage daily staffing demands.
Multiskilled crews completed work in approximately 22% to 38% fewer workdays than a modeled single-trade labor strategy was estimated to require. Restricting workers to one trade, by comparison, required 28% to 62% more workdays to accomplish the same work.
The analysis also found that on 73% of project days, a single-trade staffing strategy would have left at least one trade without sufficient available labor compared with multiskilled crews. On the busiest project days, the single-trade approach required more than one-third additional staffing.
Researchers documented 80 unique trade and skill combinations across 18 trades. Multiskilled workers performed an average of 3.2 different trades or skills over the course of their projects.
Three Studies Document Workforce Performance Gains
The schedule findings build on two earlier reports in the national multiskilling research series, which examined workforce utilization and productivity.
Across the three studies, researchers found:
Workforce utilization: Multiskilled crews increased their share of time directly advancing construction work by 39% and reduced waiting and idle time by 68%.
Productivity: Controlled field trials found that multiskilled workflows increased production rates by 37% to 50% and completed closely sequenced construction work involving frequent trade handoffs approximately 30% faster.
Staffing and schedules: Project labor records demonstrated the potential for substantially shorter schedules and greater flexibility to meet daily labor needs, helping contractors make better use of available workforce capacity.
The research emphasizes that these improvements do not depend on individual craft professionals performing tasks faster or working harder. Instead, multiskilling allows appropriately trained and qualified workers to apply a broader range of skills, reducing delays between work activities and helping contractors maintain progress as project demands change.
Researchers Emphasize Training and Worker Qualifications
“This research gives the construction industry something it has needed for a long time: measurable evidence of how workforce flexibility translates into project performance,” said Brian Lines, Ph.D., P.E., principal investigator and associate professor at the University of Kansas. “The benefits come from giving qualified workers the flexibility to apply their skills across multiple tasks, reducing unnecessary delays and keeping projects moving even with workforce needs change. This approach offers significant potential to improve project delivery in an industry facing persistent workforce constraints.”
ABC said the findings also have implications for workforce and construction policy, including the recognition of demonstrated worker competencies and expanded training and upskilling opportunities.
“The research also offers an important opportunity to inform workforce and construction policy,” said Bellaman. “With significant public and private construction investment depending on the availability of skilled craft professionals, ABC calls for policies that recognize demonstrated worker competencies, expand training and upskilling opportunities and preserve the flexibility of qualified workers to perform work safely across multiple skills and trades.”
The national multiskilling research series was conducted by the Simplar Foundation in collaboration with Arizona State University, the University of Kansas and the University of North Carolina at Charlotte.
To explore the full research series, visit simplarfoundation.org/multiskilling. To learn more about ABC’s workforce productivity initiatives, visit abc.org/multiskilling.